Audience: everyone who scores, reviews, or reports on register risks.

How scores work

A score is likelihood × impact. Each is rated on five levels, so a score runs from 1 to 25 - the higher, the more urgent.

Level Likelihood Impact
1 Rare Negligible
2 Unlikely Minor
3 Possible Moderate
4 Likely Major
5 Almost certain Severe

Scores fall into four bands. A score on a boundary belongs to the higher band.

Band Score range
Low 1-4
Medium 5-9
High 10-16
Critical 17-25
  • Inherent risk is the risk as it stands, before treatment.
  • Residual risk is what's left once the treatment is in place.

A risk needs both a likelihood and an impact to be scored; until then it shows Not scored. Scores and bands are always calculated from the likelihood and impact, so they can't drift out of step with them.

Field values

Status

Value Meaning
Open An active risk you're managing
Closed No longer applies or fully resolved; hidden from the register by default
Archived Kept for the record but out of day-to-day view

Review status

Value Meaning
Draft Being written or scored
In review With a reviewer
Changes requested Sent back for changes
Approved Signed off

Treatment

Value Meaning
Mitigate Reduce likelihood or impact with controls
Accept Live with the risk as it is, with a recorded decision
Transfer Shift it to another party, for example through insurance or contract
Avoid Stop the activity that causes the risk
Not treated No treatment decided yet

Control role

Value Meaning
In place An existing control already reducing the risk
Planned treatment A control planned as part of the risk's treatment

Monitoring

Value Meaning
Monitored by Relyance At least one policy is linked; its issues show on the risk
Not monitorable The risk can't be actively monitored on the platform; track it through its controls, treatment, and reviews
Not yet assessed No policy linked yet

Applies to

A risk can apply to any mix of: Asset, Identity, Vendor, Service, Repository, Domain, AI model, AI agent, AI use case, MCP server, DSR, and Assessment. A risk with nothing selected applies across the organization.

The risk library

The library ships about 90 risk scenarios, written to be added as they are and refined afterwards:

Domain Scenarios Examples
Privacy 23 Processing without valid consent, purpose creep, over-retention, late access requests, breach notification missed
Security 30 Secrets in source code, missing MFA, excessive privileges, unencrypted data, unpatched vulnerabilities, misconfigured cloud storage
AI 23 Prompt injection, data disclosure in AI responses, excessive agent permissions, biased training data, AI deployed without an impact assessment
Third party 15 No data processing agreement, unapproved sub-processors, AI providers training on your data, unlawful cross-border transfers

Each library risk comes with:

  • A title and a description of the scenario and its consequence.
  • A default likelihood and impact.
  • Which of confidentiality, integrity, and availability it threatens.
  • A suggested treatment.
  • The framework controls that address it - only controls Relyance ships, so the mapping works in every workspace.
  • Public references it draws on, such as NIST SP 800-30, ISO/IEC 29100, or the MIT AI Risk Repository.

Framework coverage

Library risks map to controls across more than 80 regulations and standards. The most widely mapped are:

  • Security - CIS Critical Security Controls v8.1, PCI DSS, NIST SP 800-53, ISO/IEC 27001, the HIPAA Security Rule, NYDFS Part 500, NIST CSF 2.0, NIST SP 800-171, DORA, and NIS2.
  • Privacy - GDPR, ISO/IEC 27701, CCPA, ISO/IEC 29100, ISO/IEC 27018, GLBA, the NIST Privacy Framework, UK GDPR, LGPD, and India's DPDP Act.
  • AI - the EU AI Act, ISO/IEC 42001, the OWASP AI and ML Top 10 lists, Google SAIF, the NIST AI RMF, and MITRE ATLAS.

The Suggested view shows only the library risks whose controls belong to frameworks you have enabled; All shows the whole library.